Understanding Delivery, TPI Inspection, Installation & Onsite Warranty Wording in Tenders
Who pays Third-Party Inspection charges? Does warranty start on delivery date or final commissioning? Learn how 3 lines inside ATC change real project costs dramatically.
In This Guide (Quick Navigation)
Profitable bids often turn loss-making post-award because teams quoted product hardware cost without pricing inspection fees, installation consumables, or multi-year onsite warranty response SLAs hidden inside Delivery/Inspection clauses.
Meaning & Definition
Delivery, Inspection & Warranty clauses stipulate exact lead times, consignee unloading duties, lab/third-party verification (RITES / EIL / BIS / Consignee), commissioning sign-offs, and defect rectification windows.
Why It Matters for Bidders & Suppliers
Pre-Dispatch Inspection (PDI) can consume 10–18 days of your 30-day delivery timeline—if your ATC does not explicitly pause delivery days during inspection wait times, you face automatic late penalty deductions.
Detailed Explanation & Procurement Rules
Critical Nuances Inside Delivery & Warranty Clauses
Check whether Delivery Days run from "Date of Contract Generation on GeM" or "Date of Technical Drawing/Site Clearance Approval". Note also whether "Installation & Commissioning" includes civil foundation, earthing, cabling, and training at buyer premises.
For Warranty, distinguish clearly between Comprehensive Onsite Warranty (you supply ALL spare parts, labour, travel, and engineer visits FREE for 3–5 years) versus Manufacturer Return-to-Bench Warranty. Check whether warranty clock starts from "Commissioning Date (CRAC)" vs "Delivery Date" on staggered projects.
Step-by-Step Process
-
1
Inspect whether Third-Party Inspection (
TPI/RITES/STQC) charges are payable by Buyer or Seller—many PSU bids mandate seller bears inspection charges (~0.5%–1.5%). - 2 Verify consignee PIN codes across ALL pages of the Bid PDF so multi-district unloading logistics are costed.
- 3 Build AMC/CMC or year-3-to-5 extended OEM onsite warranty cost explicitly into Year-1 bid price when BOQ demands 3 or 5 years Comprehensive Warranty.
Common Mistakes to Avoid
- ⚠Dispatching material straight to a buyer depot when ATC clearly mandates Pre-Dispatch Inspection Call Notice BEFORE dispatch (
Rejection at site!).
Frequently Asked Questions
If buyer site civil readiness is delayed by 4 months, is supplier fined LD for delayed installation?
No—document "Site Non-Readiness" promptly in writing with Consignee photos/emails and request formal Delivery/Installation Period Extension (EOT) without LD.