Bidding & Participation Updated 10 Nov 2026
3 min read · 434 words

How Evaluators Calculate "Similar Work" (One 80%, Two 50%, Three 40% Works) & Enhancement Factors

Need ₹80 Lakh single-order experience for a ₹1 Crore tender? Check whether two ₹50 Lakh works or three ₹40 Lakh works qualify you under the classic 80/50/40 benchmark.

Similar Work (80% / 50% / 40% Rule) & Experience Evaluation Formula
By Raghavendra Kulkarni Reviewed by SCL Procurement Legal & Compliance Desk
Portal Coverage
CPPP, State PWD & GeM
Section
Bidding Process
Access
Free Open Guide
Standards Status
Verified 2026 Rules
In This Guide (Quick Navigation)

Almost every infrastructure, turnkey, and high-value supply tender relies on the "Three Similar Completed Works @ 40%, OR Two @ 50%, OR One @ 80%" benchmark pioneered in CPWD & CVC works procurement manuals.

Meaning & Definition

On an Estimated Cost E (say ₹100 Lakh), a bidder usually qualifies on experience by completing during the preceding 7 years (ending last day of previous month): Three similar completed works each >= 40% (₹40L each), OR Two >= 50% (₹50L each), OR One >= 80% (₹80L).

Why It Matters for Bidders & Suppliers

Bidders often add ten ₹10 Lakh contracts together expecting ₹1 Crore to qualify—evaluators reject cumulative bundling unless the tender explicitly allows cumulative past performance (e.g., GeM Past Performance 30%–80% qty)!

Detailed Explanation & Procurement Rules

Similar Work Definition vs. Exact Value Threshold

"Similar Work" is strictly defined in NIT/Eligibility (e.g., "Supply & Commissioning of On-Grid Solar Plant" or "RCC Multistorey Building Construction"). Supplying furniture does NOT prove "Similar Work" for laboratory equipment unless NIT widens scope.

On CPWD/NHAI Works Tenders, completed work values from earlier years (up to 7 years) are normally brought to current costing level using simple enhancement (typically @ 7% per annum from actual completion date to deadline—ONLY when explicitly printed in NIT/BDS!).

Step-by-Step Process

  1. 1 Check whether your tender uses "80/50/40 Single-Contract Benchmarks" (CPWD/Works/Custom RFPs) vs "Cumulative % Quantity Supplied" (common on GeM Catalog Bids).
  2. 2 Verify the exact Lookback Window (Last 3 FYs vs Last 5 Years vs Last 7 Years ending month prior to NIT).
  3. 3 Select your top 1, 2, or 3 clean, verified Completed Works matching BOTH rupee value AND explicit "Similar Work" wording.
  4. 4 Check if MSE/Startup Exemption applies—on non-safety goods/services, approved MSE/Startup flags relax prior experience criteria.

Practical Real-World Examples

Evaluating a ₹2.0 Crore Municipal Water Pipeline Tender

Scenario: Estimated Cost = ₹2.0 Cr. Thresholds: 1 work >= ₹1.60 Cr (80%), OR 2 works >= ₹1.00 Cr each (50%), OR 3 works >= ₹0.80 Cr each (40%). Contractor A holds completed certificates of ₹92L, ₹85L, and ₹82L; Contractor B holds five works of ₹45L each.

Outcome: Contractor A QUALIFIES (3 works each >= ₹80L)! Contractor B FAILS even though total = ₹2.25 Cr, because individual works failed the ₹80L floor.

Common Mistakes to Avoid

  • ⚠Mixing two separate Purchase Orders under two different tenders/departments to pretend they constitute "One Work >= 80%".
  • ⚠Claiming 7% annual enhancement automatically where the specific state/PSU NIT did NOT include an enhancement clause.

Frequently Asked Questions

Can a Sub-Contractor use back-to-back work done under a Principal Contractor for 80/50/40 qualification?

Most Central/PSU NITs reject private back-to-back sub-contractor certificates unless the sub-contract was formally approved in writing by the original Government Department AND verified by official TDS/Completion records.

Official References & Government Sources

Editorial Verification & Publishing Metadata
Published: 20 Oct 2026 · Last Reviewed: 10 Nov 2026
Author: Raghavendra Kulkarni · Compliance Review: SCL Procurement Legal & Compliance Desk