Measurement Book (MB) & Running Account (RA) Bills in Civil & Infrastructure Tenders

Understand how e-MB Measurement Books verify completed physical civil quantities before Running Account (RA) interim contractor payments are released.

What Is Measurement Book (MB) & Running Account (RA) Bill? — Indian government procurement term reference guide
By SCL Regulatory Research Desk Reviewed by Raghavendra Kulkarni
Portal Coverage
GeM, CPPP & State Portals
Section
Terminology
Access
Free Open Guide
Standards Status
Verified 2026 Rules
In This Guide (Quick Navigation)

In civil works, municipal roads, and electrical projects spanning months, contractors receive periodic interim payouts through Running Account (RA) Bills backed strictly by verified entries inside an official Measurement Book (MB / e-MB).

Meaning & Definition

A Measurement Book (MB) is an auditable engineering ledger (now digitized as e-MB in CPWD/PWDs) where the Junior Engineer/Assistant Engineer physically measures length, breadth, depth, concrete grade, or cable metres executed at site before releasing progress payments.

Why It Matters for Bidders & Suppliers

Without joint measurement sign-off inside the MB + mandatory material quality cube/bitumen test certificates, treasury software halts RA bill payment cleanly.

Detailed Explanation & Procurement Rules

Deductions Shown on Every RA Bill Voucher

Expect statutory deductions on every RA bill: Income Tax TDS (1% individual/HUF, 2% companies under Sec 194C), GST-TDS (2% under Sec 51), BOCW Labour Cess (1%), Security Retention (as per contract), and any Secured Advance adjustment.

Common Mistakes to Avoid

  • ⚠Failing to accompany site engineers during initial buried foundation/trench measurements before backfilling earthwork—unmeasured concealed work faces audit disallowance!

Frequently Asked Questions

What is Secured Advance in RA billing?

On qualifying large CPWD works, buyers advance up to ~75% of assessed non-perishable material cost (steel/cement) stacked cleanly at site against indemnity bonds before installation.

Official References & Government Sources

Editorial Verification & Publishing Metadata
Published: 12 Oct 2026 · Last Reviewed: 10 Nov 2026
Author: SCL Regulatory Research Desk · Compliance Review: Raghavendra Kulkarni