How CAG & Departmental Audits Inspect Government Contracts—And How Suppliers Protect Payments
Executing verbal extra work for an engineer without a written Sanctioned Deviation Order invites painful Audit Recoveries years after completion. Guard your files like an auditor.
In This Guide (Quick Navigation)
Unlike private deals settled once invoices clear, public contracts remain subject to Internal Accounts Audit, Vigilance, and Comptroller & Auditor General (CAG) scrutiny for years after final completion.
Meaning & Definition
Procurement Audit Scrutiny evaluates whether deliverables matched tendered specifications, whether Extra/Substitute quantities held prior written Competent Authority approval, whether Liquidated Damages were waived without justification, and whether statutory taxes (GST/BOCW/TDS) were verified.
Why It Matters for Bidders & Suppliers
When an audit paragraph flags "Unapproved Excess Quantity" or "Missing Completion/Test Records", departments deduct recoveries directly from your ongoing contracts or pending PBG!
Step-by-Step Process
-
1
NEVER perform extra BOQ quantities (
> contract deviation limit) or substitute specifications purely on verbal engineer promises—obtain written Revised / Extra Item Sanction cleanly beforehand. -
2
Archive full Contract Execution Folders (
Award, Drawings, Lab Reports, e-MB Extracts, Deviation Sanctions, Tax Challans, CRAC, PBG Release) cleanly for at least 8 financial years. -
3
Reconcile any post-award GST Rate reduction (
e.g. if GST drops 18% to 12%) promptly—retaining surplus tax credit invites CAG unjust-enrichment recovery!
Common Mistakes to Avoid
- ⚠Accepting unofficial verbal specification swaps ("Supply local switchboard instead of Schneider; engineer said ok")—auditors flag Rate Difference Recovery years later!
Frequently Asked Questions
Can a department withhold PBG release because an old audit paragraph is unresolved?
Departments frequently hold disputed balances pending Audit Para settlement unless backed by clear verified documentary compliance proving zero lapse by supplier.