Liquidated Damages (LD) in Government Tenders: 0.5% Weekly Penalty & 10% Cap Formula

How Liquidated Damages (LD) deductions work on delayed tender deliveries: 0.5% per week calculation, GST impact on LD, 10% cap, and Extension of Time relief.

What Is Liquidated Damages (LD) in Tenders? — Indian government procurement term reference guide
By SCL Regulatory Research Desk Reviewed by Raghavendra Kulkarni
Portal Coverage
GeM, CPPP & State Portals
Section
Terminology
Access
Free Open Guide
Standards Status
Verified 2026 Rules
In This Guide (Quick Navigation)

Liquidated Damages (LD) are pre-agreed monetary deductions charged by a public buyer when an awarded supplier delivers goods or finishes contract milestones past the stipulated Completion Date.

Meaning & Definition

Across GeM, CPPP, and PSUs, standard LD runs at 0.5% per week (or part of a week) of the value of the delayed portion of supplies/works, normally capped at a maximum of 10% of contract value.

Why It Matters for Bidders & Suppliers

Even a 3-week shipping delay cuts 1.5% straight out of net invoice profit unless you apply proactively for Extension of Time (EOT) for genuine Force Majeure or buyer delays.

Detailed Explanation & Procurement Rules

Delayed Portion vs. Whole Order LD

Fair GFR & GeM rules charge 0.5%/week ONLY on the delayed portion if partial deliveries were usable independently (say 80 out of 100 units arrived on time, only 20 late)—check GTC/SCC carefully!

Common Mistakes to Avoid

  • ⚠Submitting late invoices silently without obtaining a Formal EOT amendment BEFORE shipping—treasury accounts software automatically deducts LD!

Frequently Asked Questions

Is LD capped at 10%?

Yes, most standard GFR & GeM contracts cap total Liquidated Damages at 10% of the undelivered/contract value before termination rights activate.

Official References & Government Sources

Editorial Verification & Publishing Metadata
Published: 12 Oct 2026 · Last Reviewed: 10 Nov 2026
Author: SCL Regulatory Research Desk · Compliance Review: Raghavendra Kulkarni