Risk & Cost Purchase Clause in Government Tenders: Liability Upon Contractor Default
What happens if a winning supplier fails to deliver and the buyer triggers Risk and Cost Purchase from L2: extra cost recovery, PBG forfeiture, and notice periods.
In This Guide (Quick Navigation)
Under the Risk and Cost Purchase Clause, if an awarded contractor defaults or refuses delivery after receiving a valid Work/Supply Order, the buyer can cancel the contract and procure the balance goods/works from an alternative supplier—recovering any higher extra price directly from the defaulting vendor!
Meaning & Definition
Enshrined in CPWD, Railways, Defence, and GeM GTC contracts, Risk Purchase protects public works from stalling without losing taxpayer funds.
Why It Matters for Bidders & Suppliers
Walking away from a loss-making L1 contract after award does NOT cap your loss at the 3%–5% PBG—the department can legally demand the full price gap paid to the replacement L2/L3 supplier!
Detailed Explanation & Procurement Rules
Notice Requirement Before Risk Purchase
Departments must normally issue formal Cure Notice / Show-Cause Termination Notice first before re-awarding at the defaulting contractor's risk and cost.
Common Mistakes to Avoid
- ⚠Thinking "worst case they forfeit my 5% PBG"—in sharp price surges, Risk & Cost damages can exceed 20%–30% of contract value!
Frequently Asked Questions
Does Risk Purchase apply if the buyer caused the delay (missing site handover)?
If delay resulted strictly from Force Majeure or buyer non-readiness documented promptly via written EOT requests, Risk Purchase generally cannot be enforced arbitrarily.